“The Metro Cool” – Commercial System Replacement

Metro Plaza, a 15-story commercial complex housing multiple corporate offices, was struggling with an aging HVAC system that was:

  • 18 years past its recommended service life

  • Consuming 45% more energy than modern systems

  • Causing frequent tenant complaints about inconsistent temperatures

  • Requiring monthly emergency repairs during peak business hours

  • Creating hot and cold zones throughout the building

The management needed a solution that would minimize business disruption while delivering immediate improvements in comfort and efficiency.

Strategic Phased Replacement

Phase 1: Comprehensive Energy Audit & System Design

  • Conducted detailed load calculations for each floor

  • Analyzed existing ductwork and ventilation requirements

  • Designed a modular system allowing phased implementation

Phase 2: Central Plant Upgrade

  • Installed two new 150-ton Trane centrifugal chillers with variable speed drives

  • Implemented high-efficiency cooling towers

  • Upgraded pumping systems with smart controls

Transformational Performance & Savings

  • Immediate Energy Reduction: 42% decrease in monthly energy consumption

  • Enhanced Tenant Comfort: Consistent temperature maintained throughout all floors

  • Zero Business Disruption: All work completed during off-hours and weekends

  • Reduced Maintenance Costs: 75% decrease in emergency service calls

  • Increased Property Value: Modern HVAC system became a key leasing feature